Portfolio business case

Region Group: a solar canopy portfolio across your centres

We screened Region's centres for large, flat, sealed car parks, then drew and priced three of them to scale. This is what a solar canopy programme across the portfolio looks like, and what it does for the assets.
Canyon solar canopy drawn to scale on a Region Group centre
Canyon canopy drawn to scale, Central Highlands Marketplace, Emerald QLD.
15
Centres screened
~10.8 MWp
Portfolio potential
$24-29M
Indicative, ex-GST
~11,000 t
CO2 avoided / yr
The interest is already in your centres. Retailers keep raising solar with us, and because the natural site is the car park, the decision comes back to the landlord to enable. Region is the one party that can act on it, once across the portfolio rather than store by store.

Three centres, drawn and priced

These are not desktop guesses. Each canopy below was drawn to scale on the centre's actual car park and priced through our engine. Figures are preliminary, ex-GST, subject to site assessment. Across just these three: 3.3 MWp, about 4.8 GWh a year generated on site, for roughly $6.8M of base scope.

Central Highlands MarketplaceEmerald, QLD
Prelim PP-RG-001
Canyon canopy drawn to scale on Central Highlands Marketplace
1.52 MWpSystem size
~2.28 GWh/yrGenerated on site
6,338 m²Canopy coverage
1,944Solar modules
$3.00MBase scope, ex-GST ($1.97/W)
$3.40MWith EV charging, ex-GST
Raymond Terrace MarketplaceRaymond Terrace, NSW
Prelim PP-RG-003
Canyon canopy drawn to scale on Raymond Terrace Marketplace
1.33 MWpSystem size
~1.86 GWh/yrGenerated on site
5,547 m²Canopy coverage
1,854Solar modules
$2.67MBase scope, ex-GST ($2.00/W)
$2.91MWith EV charging, ex-GST
Lavington SquareLavington (Albury), NSW
Prelim PP-RG-002
Canyon canopy drawn to scale on Lavington Square
465 kWpSystem size
~0.65 GWh/yrGenerated on site
1,936 m²Canopy coverage
714Solar modules
$1.11MBase scope, ex-GST ($2.39/W)
$1.35MWith EV charging, ex-GST
Base scope is the canopy structure, install, civil, lighting, safety and engineering. EV charging is shown as an option. Site transport, trenching and battery are not included and can be added.

What the canopy does for the asset

Lifts asset value and rating

A solar canopy is hard, disclosable infrastructure. It strengthens each centre's NABERS and sustainability position and gives Region a real Scope 2 lever for AASB S2 climate reporting, now mandatory for large entities.

A revenue line, not just a cost

Generation on site offsets common-area load (mall lighting, HVAC, car park) and opens an on-sold-power or embedded-network revenue opportunity to the anchor tenants, with EV-charging revenue as demand grows.

Shade that lifts the centre

Covered parking is a visible shopper amenity: protection from sun, heat and hail, a better arrival, and support for dwell time, foot traffic and tenant retention. Across regional QLD and NSW, that shade matters.

A platform, not just panels

The same structure also carries LED lighting, security and CCTV, and is battery-ready for demand management. None of that is in the prices above, and none of it needs a separate build; the canopy is engineered to take it.

Proven with the retailers in your centres

Canyon Solar factory-builds solar canopies that turn large car parks into on-site power generation and shade. We have delivered them for Woolworths, across six sites, and for IGA, AstraZeneca and CSIRO. The canopy below sits over an IGA supermarket car park, the same kind of anchor that trades across Region's portfolio.

IGA Baranduda solar canopy
IGA Baranduda, VIC. A Canyon Solar delivery.

The Grand Canyon

For the main lots, the standout design is the Grand Canyon: a continuous, full-coverage canopy with no gaps over the driving lanes. It gives the highest solar density in our range and a clean roofline that makes the car park look like a designed part of the centre, not an afterthought.

Grand Canyon full-coverage solar canopy render
Grand Canyon, a continuous full-coverage canopy with integrated battery and EV charging.

The rest of the portfolio at a glance

Beyond the three above, we desktop-sized the wider shortlist from each centre's GLA. Together the 15 centres represent roughly 10.8 MWp and $24-29M of indicative solar canopy, a programme that can be staged centre by centre.

CentreLocationAnchorsSystemIndicative
Lavington Square Drawn & pricedLavington (Albury), NSWWoolworths; Big W465 kWp$1.11M
Central Highlands Marketplace Drawn & pricedEmerald, QLDWoolworths; Big W1.52 MWp$3.00M
Raymond Terrace Marketplace Drawn & pricedRaymond Terrace, NSWWoolworths; Big W1.33 MWp$2.67M
Marketplace Warner DesktopWarner (Brisbane), QLDWoolworths; ALDI~812 kWp$1.6-2.0M
Brassall SC DesktopBrassall (Ipswich), QLDWoolworths; ALDI~719 kWp$1.7-2.1M
Katoomba Marketplace DesktopKatoomba, NSWWoolworths; Big W~676 kWp$1.6-1.9M
Mount Isa Village DesktopMount Isa, QLDColes; Kmart~670 kWp$1.6-1.9M
Marian Town Centre DesktopMarian (Mackay), QLDWoolworths~657 kWp$1.5-1.9M
Muswellbrook Fair DesktopMuswellbrook, NSWColes; Harvey Norman~614 kWp$1.4-1.8M
Belmont Central SC DesktopBelmont (Lake Macquarie), NSWWoolworths~558 kWp$1.3-1.6M
Whitsunday SC DesktopCannonvale, QLDColes~539 kWp$1.3-1.5M
Worongary Town Centre DesktopWorongary (Gold Coast), QLDColes~496 kWp$1.2-1.4M
Griffin Plaza DesktopGriffith, NSWColes~496 kWp$1.2-1.4M
Drayton Central SC DesktopDrayton (Toowoomba), QLDWoolworths~474 kWp$1.1-1.4M
Greenbank SC DesktopGreenbank, QLDWoolworths~397 kWp$0.9-1.1M
Desktop figures are derived from centre GLA and are indicative only. Drawn-and-priced figures come from a scaled layout and our pricing engine. All subject to site assessment.

How to proceed

Own it (CAPEX)

Region holds the canopies and all the generation, on a 30-year design life, staged centre by centre across the portfolio.

Hardware as a service (OPEX)

$0 upfront. A service agreement arranged through an independent finance partner; Region keeps the generation and pays from the savings and revenue.

Every canopy is engineered, factory-built and installed by the team that has delivered 16 projects across three states.

A short working session to confirm the priority centres, validate the layouts on the actual title boundaries, and firm the tariff, common-area load and revenue assumptions with Region's real figures. We can draw and price any other centre in the portfolio live, in minutes.